Project 04 · Case study
Inclining Transparent Walkway (Vibram Senior Design)
Vibram wanted to film shoe soles from under a walking person; we delivered a transparent walkway inclining 0–40° with a 500 lb design load.
Getting to delivery meant killing our leading mechanism two-thirds through and verifying its replacement — the work of four rounds of FEA across six months.
What Vibram asked the walkway to do
The load requirement carried a safety factor of two on the person’s weight, increasing the maximum weight for the walkway from 250 to 500 pounds. The lift had to be mechanical — the $2,500 budget effectively ruled out electrical solutions anyway, and the customer did not want electricity. The finished unit also had to fit through a door into the facility, and that requirement is what set the walkway’s width.| Requirement | Target | Achieved | Verified by |
|---|---|---|---|
| Incline in fixed steps (relaxed from 0–45° in 5° steps) | 0–40°, 10° steps | met — bench pins natively index 0–40° in 10° increments, one bolt pair per angle | delivered device, demonstration |
| Support a walking person with SF 2 | 500 lb | by analysis — FEA passed at 500 lb; the walk-on peaked at about 450 lb | SolidWorks FEA + hand calcs + walk-on test |
| Fully mechanical lift, no electricity | — | met — bench pins + gas struts + hand-cranked camera carriage | inspection of delivered design |
| Transparent 66 × 24 in walkway | 66 × 24 in | met — 0.75 in cast acrylic, 24 × 66 in | BOM + delivered device |
| Operable by one person (two acceptable) | 1 person | met — one pull releases both bench pins; gas struts nearly self-lift the ramp | use during validation; no formal test documented |
| Railings on top of the walkway | — | met — parallelogram handlebars, back bar vertical at any angle | delivered design |
| Removable acrylic, modular, stock parts | — | met — toggle clamps release the panel; all-bolted 8020; nearly every part off the shelf | delivered design |
| Easy to move on wheels | — | met — retractable casters | delivered design; no mobility test documented |
| Camera perpendicular to the walkway at all times | 90° | met — rail rides parallel to the acrylic frame at every angle | presentation evaluation slide |
| Fit through a door into the facility | — | met — delivered into the Boston Connection Lab | delivery |
Concepts for the lift mechanism
The lifting and indexing concepts on the table: hydraulic, jack, scissor jack, two pulley variants, winch, crank, linear slide, lead screws, a simple human lift, and a beach-chair locking mechanism. The scissor jack was mine.I organized the House of Quality that scored all of it: fail-safe design ranked most important, and the specification weights put safety factor first at 16% (design goal 2) with maximum cost second at 14% ($2,500). The Pugh analysis reused those HoQ weights, and the manual human lift scored highest on simplicity and low cost. The candidates also got deflection numbers: we modeled the jack design as a cantilever with a composite acrylic-and-aluminum modulus of about 2.19 × 10⁶ psi, where a 400 lb load at the end of the walkway deflected it 0.743 inches with the jack 2 feet along — moving the jack to 3 feet cut that to 0.27 inches. The full matrix and weighting method are in the House of Quality report.
That’s the design we carried out of the fall: a manual lift with lawn-chair indexing — machined grooves in steel tubing as index points, a steel bar slotting in, clevis-ended aluminum struts up to the acrylic cage. The fall down-select and design are documented in the fall halfway report.
Why we dropped the beach-chair mechanism
Two 1,200 lb gym benches as the lift
What replaced it was prefabricated: two home gym benches, modified and bolted into the base frame. Each bench is rated 1,200 lb by its manufacturer, its alloy-steel pin mechanism natively indexes to 40 degrees in 10-degree increments, it’s a stock product Vibram can repurchase, and it hits the top two House of Quality criteria — fail-safe design and 300+ lb. The lift that replaced months of our own mechanism design cost $69.99 a bench. We trusted the 1,200 lb rating as a starting point, then verified it — FEA before assembly, physical testing after.
Integrating them was one of my subsystems, and it reused the benches’ own hardware: the pads came off, and their existing screw holes were designed to line up with the 8020 — each bench’s inclinable portion bolts to the acrylic frame, its base into the base frame. The subsystem down-selection is in the spring 2025 presentation.
The two gas struts — IAQWE 28-inch, 120 lb heavy-duty — are sized to almost entirely lift the ramp by themselves from the compressed state; with the pins out, the user adds only a few pounds of force, and the pins hold everything the rest of the time. The load path at incline was the late fix: the original plan had the benches cantilevering the walkway’s weight, I calculated that was not feasible, and removable steel tube supports were added late. Each tube bolts to the sides of both ramp frame and base, and I calculated the bolt positions so each pair yields exactly 10, 20, 30, or 40 degrees — on the BOM they’re 4 ft and 6 ft carbon steel rods with ball-joint rod ends, the short and long struts the user installs for the height they want.
Why the plate is 0.75-inch cast acrylic
Four transparent surfaces made the material table: polycarbonate, acrylic, tempered glass, and structural laminated glass.| Property | Polycarbonate | Acrylic | Tempered / laminated glass |
|---|---|---|---|
| Yield strength | ~60 MPa | ~70 MPa | 120–200 MPa |
| Elastic modulus | 2.3 GPa | 3.2 GPa | 70 GPa |
| Impact resistance | 250× glass | 17× glass | baseline |
| Scratch resistance | Mohs 3 | Mohs 3.5 | Mohs 7 |
| Refractive index | ~1.58 | ~1.49 | ~1.52 |
We shipped 0.75 in. Half-inch acrylic deflected an undesired amount; 1-inch was deemed too heavy for the average user to lift; 0.75 in withstands 300+ lb with minimal deflection and stays light enough to lift with the gas strut assist. The fall analysis figures and the fall BOM are in the fall final report.
Every risk was calculated
This was being delivered to a customer for their use, and I did not feel comfortable accepting risks and leaving them unaddressed — every identified risk got a hand calculation plus FEA verification. Four rounds of FEA ran in SolidWorks Simulation across six months — too many complex geometries to stress-test accurately by hand. The failure points, analyzed one by one: the acrylic breaking, the frame holding it, the steel supports connecting frame to base, and the base itself. The gas strut load came from regular cantilever equations, the bolted supports got simple hand calculations first and FEA after, and the acrylic-and-frame FEA covered stress and deflection plus fatigue. One structural decision was made on ethics grounds before any analysis: no welding. None of us had the training or certification to make safe, consistent welds — NSPE rule 2, practice only in your field of competence — so the structure is entirely bolted 8020, a material all five of us knew well. That vote was unanimous.Rails, clamps, and casters around the acrylic
The stack, end to end: the 8020 base, the benches bolted into it, the acrylic ramp frame bolted to the bench tops, and the handrails, gas struts, end supports, and camera rail all hanging off the ramp frame. The acrylic rests on 1 × 1 in internal beams inside a 2 × 2 in 8020 perimeter, where rubber tape and toggle clamps keep it from moving while still letting a user pull the panel out in seconds — Vibram’s removability requirement.
The camera system under the walkway
I led the camera research, and the requirement was strict: the camera below must stay perpendicular to the walkway at all times. In the spring the camera design questions went to me and a teammate, and I ran the subgroup that answered them — three of us, meeting notes mine. The recording decisions came first: a phone rather than a dedicated camera, because capture and export are easier, there’s no camera to buy, and it’s simpler for the user; continuous video through the phone’s native camera app instead of triggered stills, so Vibram can extract whatever they need from the footage; no data cable — the videos stay on the phone and export digitally; and the camera stays unmoved while filming so the picture is stable, mounted as far below the acrylic as the geometry allows. The phone mount we bought instead of printing: friction-fit prints aren’t universal and crack, tensioned universal prints rely on rubber bands, and a purchased universal mount cost about $16 — I ordered it. For driving the carriage we weighed a belt drive, very smooth but needing at least 10 feet of belt; a pulley-and-spool, very simple but easy to break; and a motorized drive, scrapped outright because this machine was to have no electromechanical components. What shipped is a phone holder on a linear rail under the acrylic, connected to a gear system: the user cranks the holder out from under the frame — the rail extends past the end of the ramp — loads their phone, cranks it back under, and controls it by remote while it’s underneath. The crank-out exists because I did not want the user to have to reach under and potentially put themselves in a pinch point or any danger.
Machining and assembly
We had essentially all of McMaster-Carr available as well as the machine shop at the school, and that led to a ramp consisting almost entirely of 8020. Manufacturing was mostly ordering 8020, cutting it to size on the cold saw, then drilling and tapping holes in the proper places — every part personally made by the team, with me leading the manufacturing. Each hole position was measured to within 1/16 in, with a tolerance stack-up at the places where components interface — every drilled feature had to land within tolerance for the all-bolted frame to go together easily and properly. Tapping was the workflow that broke first: the initial design required tapping the ends of many 8020 bars, which took too much time and effort, so I moved joints to the side of the extrusion instead of the end and used slide-in T-slot hardware instead of tapped holes. Vendors were almost entirely McMaster-Carr, plus the gym benches from Amazon — both with very low lead times — and the acrylic quoted over email from Port Plastics and picked up. The device was machined and assembled over the course of a month. There was only budget for one physical build, so iteration happened in design: versions with and without the late steel supports, and a camera system that went through a lot of iterations.Assembling the budget in stages
In September the budget was uncertain: $500 from BU, no stated figure from Vibram, and their guidance was to pitch material purchases and design decisions with justifications whenever we asked for funding. So I assembled the budget in stages: $100 per person from the class — $500 for the five of us — an extra $700 I secured from the school that other projects weren’t using, and the remainder from Vibram after I presented the bill of materials and the design justifications. The line items, split by who paid, are in the bill of materials.
Load testing
The validation plan was simply to use it: once the walkway was assembled and all of the supports were properly in place, we tested it by having users walk on it, and it held. What we observed matched what we had predicted with the hand calculations and FEA — the comparison was qualitative, a pass/fail walk-on rather than an instrumented test. The benches’ 1,200 lb manufacturer rating got the same treatment: FEA simulation before assembly and physical testing after.Delivered to the Boston Connection Lab
What went out the door in May 2025: the 2 × 5.5 ft, 0.75-inch cast acrylic walkway in its 8020 fixture with parallelogram handrails, gym-bench lift, steel supports, gas struts, casters, and the camera rail. Nearly every part was off the shelf — this was designed on a budget that could not use custom parts. That was deliberate: repairability was a selection criterion, and we handed over all documents and information at year end so Vibram could fix anything on their own.
The ramp did its job: it supported the weight it was asked to, let video be filmed underneath without anyone reaching under the walkway, and it is still in use at the Boston Connection Lab.